Lethbridge County conducting various road and bridge rehabilitation work

Lethbridge County will be busy this September working on numerous road rehabilitation projects.

Several stretches of cement-surface roads have been identified for cement stabilization and double chip seal work due to their conditions. Projects and their timelines include:

  • RR 23-4 (Old HWY 23) between HWY 519 and TWP 10-4 (3.2 km) – begins September 1
  • River Ridge Road between HWY 3 entrance/exit and TWP 9-2 (2.2 km) – begins September 6
  • RR 21-1 (McNally Road) between TWP 8-2 and HWY 508 (3.2 km) – begins September 10
  • TWP 10-4 between HWY 845 & RR 20-1 (1.3 km) – begins September 16
  • RR 21-5 south of HWY 25 (1.8 km) – begins September 19
Image courtesy: Lethbridge County

Affected landowners will receive a letter with full details. The roads will remain open during construction but will be reduced to single-lane traffic.

Additionally, crews will be starting maintenance work on September 8th for the Kipp Bridge on Township Road 9-4 outside of Coalhurst near the CPKC railyard. A single lane will remain open but flag persons will be on site to manage traffic flow with short stops expected.

Image courtesy: Lethbridge County

This project, as well as the road rehabilitation work are all expected to wrap up by the end of September, weather permitting.